Block D2 - Construction Update - 4th August 2025
We are pleased to share the latest construction update for plots 33 to 43 in Block D2. We remain on track for a programmed completion date of September 2025, and good progress has been made across all homes within this section of the development.
As we are now within two months of your estimated completion date, we will be providing biweekly construction updates to keep you fully informed on the final stages of progress. These updates will be shared here on your customer portal and will outline remaining works, key milestones, and any changes to timelines as we move closer to handover.
At this point, the structural and internal build phases are complete for all properties. This includes installation of the timber frames, roofing, windows and doors, and the internal screed and joinery works. All first-fix electrical and plumbing installations are in place, with walls fully plaster boarded and skimmed. Kitchens are now fitted, bathrooms have been tiled, and primary sanitaryware such as basins, toilets, and showers have been installed. Decoration is advancing, with mist coats and first coats complete, and final decoration due to commence in the next period.
Externally, major works such as the formation of driveways, rear garden paving, fencing, cycle storage and bin stores are underway. Terraces are formed and balustrades have been installed, with the terrace paving to be installed, the cycle storage in the rear gardens to be erected and the works to the footpath also currently outstanding.
Outstanding works vary slightly between plots, as outlined below:
Plots 33 to 41: These plots are structurally complete and fully fitted, with final mechanical and electrical finishes currently being worked on. Floor finishes are also underway in these plots which includes fitting final flooring materials such as vinyl, carpet, or laminate, depending on specification. In addition, each of these plots will undergo a final ‘sparkle clean’, which is a detailed deep clean to prepare the homes for handover and ensure they are presented to a high standard.
Plots 42 and 43: These are slightly behind the others but remain on track. Along with floor finishes and second fix mechanical and electrical works, these plots are also undergoing the final fix of internal joinery, including installation of finishing items such as internal doors, skirts and arcs, and other small but important touches that ensure the homes are fully usable and ready for occupation.
All plots will undergo final inspections and quality checks once the remaining items are completed, and we will continue to provide updates as we move closer to handover. We understand how important clear and timely communication is at this stage, and we are committed to keeping you informed as works progress.